Incoterms decide where the seller’s cost and risk stop; lead time decides whether the tank reaches site
before the construction programme needs it. Both should be stated in the quotation with a named place
and a realistic sequence. “FOB” without a port, or “CIF” without a destination, is not a commercial term — it
is an invitation to a dispute.
Incoterms used for water tank exports
| Term | Cost / risk transfer | Best fit | What to state |
|---|---|---|---|
| EXW | Buyer collects at the seller’s premises; buyer bears export clearance and main freight. | Buyer has a strong forwarder and wants full control. | Exact pickup address, loading capability, export clearance responsibility. |
| FOB | Seller delivers on board the vessel at the named port; risk transfers when the cargo is on board. | Buyer negotiates ocean freight; common for container shipments. | Named port (e.g. FOB Nansha), container loading and export clearance scope. |
| CFR | Seller pays ocean freight to the destination port; risk transfers on board at origin. | Buyer wants freight included but arranges insurance. | Destination port, freight scope, insurance responsibility. |
| CIF | Seller pays freight and marine insurance to the destination port; risk transfers on board at origin. | Buyer wants a delivered-to-port price with insurance. | Destination port, insurance coverage/value, unloading responsibilities. |
| DAP | Seller delivers at the named place, ready for unloading; buyer handles import clearance and unloading. | Buyer wants door delivery but can clear customs. | Exact site address, access restrictions, unloading equipment. |
| DDP | Seller delivers duty-paid at the named place; seller bears import clearance and duties. | Buyer wants a fully delivered price. | Import license, duty/tax treatment, site access, customs broker. |
LONGCOM normally quotes FOB Nansha or CIF destination port. We can quote
another term if the buyer’s forwarder and import arrangements support it, but the scope must be written into the
quotation. Do not compare an FOB price with a DDP price without adjusting for freight, insurance, duty and
destination charges.
What FOB Nansha includes — and what it does not
FOB Nansha means the seller delivers the packed tank on board the vessel at Nansha port and clears export.
The buyer pays the ocean freight, destination charges and import clearance. The seller’s scope normally includes
packing, inland transport to the port, export declaration and loading on board; it does not include the
destination port charges, import duty or delivery to site.
Check the following before comparing FOB offers:
- Is the quoted price per tank or per container? What is included in the packing?
- Is the port of loading Nansha, or another port with extra inland freight?
- Who pays for container loading, lashing and any heavy-lift charges?
- Is export clearance included, and are all document fees included?
- What is the free time at the destination port, and who pays demurrage/detention?
What CIF destination includes — and what it does not
CIF means the seller pays the ocean freight and marine insurance to the named destination port. Risk still
transfers when the cargo is on board at origin, not when it arrives. The buyer normally handles import clearance,
destination port charges, inland transport and unloading. CIF is not “door delivery”; if the site is inland, the
buyer needs a forwarder or a DAP/DDP quotation.
Confirm the insurance coverage and insured value. A basic policy may not cover the full replacement value,
site delays or special risks. If the project needs extended cover, state it before shipment; it cannot be added
retrospectively.
Lead time: build the schedule backward from site need
| Stage | Typical activity | What can delay it |
|---|---|---|
| Drawing approval | Issue GA drawing, panel schedule and connection details; buyer/consultant reviews. | Late comments, missing base/connection data, unresolved standard clauses. |
| Production | Panel fabrication, fittings, crates and marking. | Material availability, drawing changes, factory loading, special fittings. |
| Inspection | Dimensional checks, trial assembly, water-fill test, third-party witness. | Inspector availability, failed test, missing records. |
| Packing / loading | Crating, loading plan, container release, loading and seal. | Container shortage, late packing changes, port congestion. |
| Ocean transit | Loading, sailing, transhipment if any, arrival at destination port. | Weather, route changes, port congestion, customs holds. |
| Site delivery | Import clearance, port release, inland transport, unloading. | Document mismatch, duty payment, truck permits, site access. |
For a standard bolted stainless tank, production is often scheduled in the range of a few weeks after
drawing approval, with inspection and packing added before shipment. The exact lead time depends on panel
thickness, fitting scope, inspection requirements and factory load. We state it in the quotation; we do not
promise a generic “20-day delivery” that ignores drawing approval and testing.
Schedule example: 500 m³ tank for a fixed site date
Assume the site needs the tank on site in 14 weeks. Work backward: allow 1–2 weeks for import clearance and
inland delivery, 3–5 weeks for ocean transit (route dependent), 1 week for loading and documents, 2–3 weeks for
inspection/packing, and 3–6 weeks for production after drawing approval. That leaves roughly 1–3 weeks for
drawing review and any tender clarification — which is often the stage that consumes the buffer. If the drawing
approval slips by three weeks, the site date slips unless production or shipping is expedited.
This example is a planning aid, not a quotation. Actual transit and production times must be confirmed
against the route, factory schedule and inspection scope.
What buyers can do to protect the schedule
- Appoint one engineering reviewer and return drawing comments in one consolidated round.
- Freeze the tank dimensions, connections and standard clauses before production release.
- Name the third-party inspector and witness points before fabrication, not after.
- Book the container and forwarder early; confirm the free time and demurrage terms.
- Prepare the site base and unloading equipment before the container arrives.
- Check the document set against the LC or contract before shipment, not after.
Payment and commercial terms
Payment terms, currency, validity and warranty are stated in the quotation and contract. They are not
inferred from the website. If the project requires a specific payment instrument, such as a letter of credit,
include the LC draft with the RFQ so the document requirements can be checked before pricing.
Common Incoterm and schedule mistakes
| Mistake | Consequence | Better approach |
|---|---|---|
| “FOB” without a port | Ambiguous inland cost and loading responsibility. | State FOB Nansha or the exact named port. |
| “CIF” without a destination port | Freight and insurance cannot be priced. | State the destination port and insured value. |
| Comparing FOB and DDP prices | Apples-to-oranges commercial comparison. | Ask for a scope matrix under one Incoterm, then compare. |
| Assuming CIF means door delivery | Buyer is surprised by destination charges and inland freight. | Clarify port-to-site scope; consider DAP if door delivery is required. |
| Starting production before drawing approval | Rework, delay and cost dispute. | Make drawing approval a formal hold point. |
| No schedule buffer for inspection | Shipment slips when a test or document fails. | Plan inspection and document review before the vessel cut-off. |