Container Loading for Water Tanks

Container loading for a sectional water tank is a sequence problem before it is a space problem.
The panels, seals, fasteners and tie rods must arrive in the order the site will build the tank, and the
container must be loaded so the first ring is accessible without unpacking the whole shipment. A loading plan
that only asks “how many panels fit” is not enough for a project site.

Which container type should the tank use?

Container Typical use Strength Limit to check
20GP Small tanks, spare panels, fittings, mixed accessories. Easy to handle; lower freight cost for dense loads. About 33 m³ internal volume; volume limits thin panels before weight does.
40GP Medium panel kits with efficient crates. More volume than 20GP; widely available. About 67 m³; check crate stack height and payload.
40HQ Most sectional panel kits; high-cube gives extra height for crates. About 76 m³; best for light, bulky panel crates. Payload normally around 26–28 t; real limit is crate layout and axle load.
Flat rack / open top Factory-welded sections or oversize items that cannot fit a closed container. Allows lifting and oversize cargo. Freight, lashing, weather protection and road permits.

The default for bolted stainless panels is a 40HQ, because the cargo is volume-limited rather than
weight-limited. A 20GP can be better for a small tank or a spare-parts order where the panel count is low and
the freight budget matters. The final choice comes from the packing list, not from a rule of thumb.

Panel weight: the number that decides the payload

Stainless panel weight is driven by area and thickness. For a 1 m² panel, the approximate weight is:

Thickness Approx. weight per m² 500 m² panel set What it means
1.5 mm ≈ 11.9 kg ≈ 5.9 t Light panels; volume and crate height usually govern.
2.0 mm ≈ 15.8 kg ≈ 7.9 t Still volume-limited in efficient crates.
3.0 mm ≈ 23.7 kg ≈ 11.9 t Weight starts to matter; check axle load and crate stacking.

These figures are for the panel only. Add seals, fasteners, tie rods, roof beams, ladders, connection
fittings, crates and dunnage. A 500 m² panel set can become a 9–14 t shipment before accessories, which is
still within a 40HQ payload but changes the centre of gravity and the lashing plan.

Planning example: 500 m³ bolted stainless tank

Assume a 10 m × 10 m × 5 m tank with 1,000 × 1,000 mm panels. The walls need about 200 panels, the floor
about 100 and the roof about 100 — roughly 400 panels before edge cuts, openings and spares. At 1.5 mm, that is
about 4.8 t of panel steel; at 2.0 mm, about 6.3 t. The crate volume, not the steel weight, usually decides how
many 40HQ containers are needed.

A practical loading plan might use two 40HQ containers: container 1 for floor panels, first wall ring,
seals and fasteners; container 2 for upper wall rings, roof panels, tie rods and accessories. For a smaller
tank, one 40HQ may be enough. The plan must be built from the approved panel schedule and the actual crate
dimensions — not from a generic “panels per container” figure.

Do not treat the example as a shipping guarantee. Panel count, crate design,
stack height, corner protection and weight distribution all change the final plan. We issue a container loading
plan with the packing list after drawing approval.

Loading sequence that supports site erection

Step Action Why it matters
1. Confirm container condition Check floor, walls, doors, seals, ventilation and cleanliness; photograph before loading. Damage and moisture claims need a baseline; dirty containers can contaminate potable components.
2. Load floor panels first Place floor bundles at the far end or in a dedicated block, marked “floor”. The floor is laid first; it should not be buried behind upper-ring panels.
3. Load first wall ring Place ring 1 panels next to the floor group, with marks visible. Site can start wall erection immediately after the floor.
4. Load upper rings in sequence Ring 2, ring 3, then roof; keep each group together and marked. Prevents a mixed pile and reduces site sorting.
5. Load long items Tie rods, roof beams and ladders on top or in a dedicated rack, restrained against movement. Long items can shift and damage panels if loose.
6. Load accessories Seals, bolts, gaskets and small fittings in labelled boxes near the door. These are needed early and are easy to lose.
7. Secure and photograph Strapping, bracing, edge protection, door seal; photograph each row and the final load. Supports insurance and gives the site a reference before unloading.
8. Seal and document Record container number, seal number, weights and package count on the packing list. Customs and receipt check depend on matching numbers.

Securing the load

  • Use steel-framed crates or properly braced timber crates; do not rely on loose strapping around a stack of panels.
  • Keep heavy crates low and distribute weight across the container floor; avoid concentrating load on one axle.
  • Protect panel edges and faces with plastic or board; do not let metal straps bear directly on the stainless surface.
  • Block and brace long items such as tie rods and roof beams so they cannot slide forward during braking.
  • Leave ventilation paths if the container may sweat; avoid trapping moisture against stainless panels.
  • Photograph the load before closing the doors; keep the images with the packing list.

Unloading at site

Confirm the site has a forklift or crane rated for the crate weights, a level unloading area and space to
store panels under cover. Do not drop crates from the container; do not store panels directly on muddy ground.
Keep seals and fasteners in a dry, shaded store. Open container 1 first and check the package count against the
packing list before signing the delivery receipt.

If the site cannot unload a full 40HQ in one shift, plan a safe temporary storage area and keep the
container secure. Demurrage and detention charges can exceed the unloading cost if the container is held
unnecessarily.

Container loading checklist

Check Acceptance
Container condition Dry, clean, no holes, doors operate, seal present; photos taken.
Package count Matches packing list; marks readable; no mixed ring groups.
Weight distribution Heavy crates low and spread; axle load within road/container limits.
Securing No movement under hand pressure; long items blocked; edge protection in place.
Accessories Seals, bolts, gaskets and small fittings in labelled boxes near the door.
Documents Packing list, loading photos and seal number recorded; electronic copies sent.